Complaints
to the European Commission <Top>
As well as (or instead of) bringing an action before
a national court, it is open to a supplier to lodge
a complaint with the European Commission in Brussels
at the following address: 200 rue de la Loi, 1049 Brussels.
The Commission is responsible for overseeing compliance
with the Procurement Directives and is used to handling
complaints from individuals and firms.
Under the Remedies Directives, the Commission may invoke
a "corrective" procedure when, prior to a
contract being concluded, it considers that a clear
and manifest infringement of EU procurement rules has
been committed. In such a case, the Commission will
notify the awarding authority and the relevant Member
State Government of the circumstances of the alleged
infringement. The Commission will set a time limit of
at least 21 days (public sector) or 30 days (utility
sectors) within which the national Government has to
respond. In practice the awarding authority, through
the medium of Government, is called upon to justify
its conduct, rectify the infringement or suspend the
award procedure.
In cases where the Commission is not satisfied with
the explanations or actions of the awarding authority
or the Member State Government, it may commence formal
proceedings against the latter under Article 169 of
the Treaty of Rome. Such an action may ultimately result
in the European Court of Justice ("ECJ") issuing
a ruling which condemns the Government in question for
failing to fulfil its Community law obligations. In
particularly serious cases, the Commission might also
ask the ECJ to grant interim measures.
Alternative Dispute Resolution <Top>
Where a dispute arises relating to a procurement procedure,
it will usually be in the interests of both sides (the
authority and the supplier) to attempt to resolve the
matter without embarking upon litigation. Hence, the
supplier in question should consider informing the authority
of its grievance, with a view to settling the matter
in an amicable way. For example, the authority might
be persuaded to remove a discriminatory technical standard
or award criterion.
Where amicable discussions fail to resolve the matter,
the parties could seek to reach a settlement through
arbitration. The parties could agree to the appointment
of an independent arbitrator drawn from a recognised
body of independent arbitrators. Addresses for such
bodies are given in the list of useful addresses at
the end of this Guidance.
Where a dispute relates to procurement by a utility,
a supplier may seek to invoke the conciliation procedure
laid down in Remedies Directive 92/13 for the utilities
sectors. Recourse to this conciliation procedure involves
the following steps:
i the supplier forwards a request for use of the conciliation
procedure to the European Commission;
ii the Commission asks the utility in question to state
whether it is willing to take part in the conciliation
procedure. The procedure can only continue if the utility
gives its consent;
iii the Commission proposes a conciliator drawn from
a list of independent persons. Both sides must state
whether they accept the conciliator and each side designates
an additional conciliator;
iv the applicant supplier, the utility and any other
relevant candidate/tenderer have the opportunity to
make representations to the conciliators; and
v the conciliators endeavour to reach an agreement between
the parties which is in accordance with Community law.
The utility or the supplier may withdraw from the procedure
at any time. Unless the parties decide otherwise, each
is responsible for its own costs.
United Kingdom<Top>
Implementation
of the Remedies Directives
In the United Kingdom, implementation of the EU Directives
on procurement has been achieved by way of the following
statutory instruments:
i the Public Works Contracts Regulations 1991 ;
ii the Public Services Contracts Regulations 1993 ;
iii the Public Supplies Contracts Regulations 1995 ;
and
iv the Utilities Contracts Regulations 1996 .
The first three sets of Regulations listed above govern
the procurement practices of Central Government, local
authorities and other public sector bodies. The Utilities
Contracts Regulations 1996, on the other hand, apply
to "utility" companies (most of them privatised)
operating in the water, energy, transport and telecommunications
sectors. (An indication of when the procurement rules
are likely to apply and the types of infringement that
may occur was given on the previous page and also Guidance
24/2001).
As well as setting out the substantive rules on procurement
procedures, the above regulations (collectively "the
Regulations") each include a section dealing with
rights of recourse to the British courts. The remedies
potentially available are described below.
The
relevant forum<Top>
Proceedings under any of the Regulations must be brought
in:
i the High Court in England and Wales; or
ii the Court of Session in Scotland; or
iii the High Court in Northern Ireland.
Such a court is located in most large or medium-sized
towns and cities throughout the United Kingdom. The
exact choice of court will depend on the location of
the authority and the complainant, but it would be usual
for the action to be brought in the court located nearest
to the authority in question or in London (if the proceedings
are to be commenced in England or Wales). Addresses
of the regional headquarters of the High Court and Court
of Session are given at the end of this Guidance.
Available
remedies<Top>
The remedies potentially available to a complainant
under the procurement Regulations fall into three categories,
which are each described in turn below.
Interim
orders<Top>
The complainant may ask the court to issue an interim
order (or "injunction"), which suspends the
allegedly defective award procedure or suspends the
implementation of any decision or action taken by the
awarding authority in the course of such a procedure.
It is important to note that such interim measures may
only be granted if the contract in question has not
been entered into between the authority and a third
party. After the contract has been entered into, the
only remedy available is damages (see Damages below).
It is therefore in the interests of the complainant
to lodge his request for interim measures as rapidly
as possible.
In order to obtain an interim order, a complainant must
first show that there is a serious case to be tried
(though not necessarily that he has a better than 50%
chance of succeeding) at the final trial. This is not
in general a difficult hurdle to overcome. More importantly,
the complainant will need to persuade the court that
the "balance of convenience" lies in favour
of granting such an order. In applying this test, the
court is likely to consider various factors, including
the following:
i whether it would cause greater hardship to grant or
refuse the order. The court might decide, for example,
that suspending the contract procedure would be against
the public interest because it would delay the provision
of important services to the public;
ii whether damages would provide an adequate remedy
to the complainant if the injunction is not granted;
iii the relative strength of each party's case.
As
the name suggests, interim measures are granted at an
interim or "interlocutory" stage in the proceedings,
without there being a full trial of the issues in question.
These issues remain to be ruled upon at the subsequent,
full trial.
Set-aside
and amendment orders
The High Court has the power to order the setting aside
(or annulment) of any decision or act taken unlawfully
in a procurement procedure. This could be the decision
to award the contract to a particular supplier or any
earlier decision in the procedure, such as the one pre-selecting
a shortlist of candidates to tender. The set-aside order
would take the form of a final injunction: that is,
one that is given at the full trial (rather than at
an interim or interlocutory stage) and which is intended
to be permanent in effect. The factors determining whether
the Court will grant such an order are likely to be
similar to the ones set out above in relation to interim
measures.
Where
there has been an infringement of the procurement rules,
the High Court may also order the awarding authority
to amend any documents. This power could be used, for
example, to require the alteration of discriminatory
technical specifications or the extension of unduly
short time limits.
Set-aside
and amendment orders, like interim measures, may only
be granted if the contract in question has not yet been
entered into.
Damages <Top>
Regardless of whether or not a contract has been entered
into, the High Court is empowered to award damages to
a supplier who has suffered loss or damage as a consequence
of a breach of the procurement rules. The Regulations
do not expand upon the principles governing the availability
and amount of damages. The only exception is under the
Regulations applicable to utilities which state that,
where the complainant establishes that an infringement
deprived him of "a real chance" of winning
a contract, he shall be entitled to damages covering
his costs of preparing a tender and participating in
the award procedure ("bid costs"). Otherwise,
British courts are likely to apply existing principles
of domestic law when considering claims for damages.
In
order to obtain damages, complainants will be required
to prove that the authority has committed a breach of
the Regulations and that this breach has caused him
harm or damage. Depending on the facts of the case,
the damages award may cover all or part of the complainant's
bid costs and/or the loss of the potential profit that
he would have made on the contract.
It
appears that a complainant will not be required to prove
that, in the absence of the breach, he would necessarily
have won the contract at stake. A reasonable chance
of winning the contract ought to be sufficient. On the
other hand, the damages award might be reduced by a
certain percentage in order to take into account the
possibility that the complainant's bid would have been
unsuccessful in any event.
Who may apply? <Top>
The rights of action laid down in the Regulations are
available to any person who sought, or who seeks, or
who would have wished, to be the person to whom a relevant
contract is awarded. In other words, the remedies are
potentially available to any supplier who had an interest
in being engaged to carry out the contract in question.
This will include suppliers who participated in the
award procedure, as well as any others who would have
done so but for the infringement.
The only further qualification is that the complainant
must be a national of and established in an EU Member
State or in certain other European countries listed
in the Regulations.
Time limit for bringing actions<Top>
Under each set of Regulations, legal actions must be
brought promptly and in any event within three months
from the date when the grounds for bringing the proceedings
first arose, unless the Court considers that there is
a good reason for extending the period within which
proceedings may be brought.
The time limit begins to run from the date when the
challenged conduct occurred. For example, if the plaintiff
is complaining that he was improperly disqualified in
a pre-qualification exercise, he would have (at most)
three months to commence any court action as from the
date of the authority's decision to exclude him. The
Court might, however, exercise its discretion to extend
the three month time limit if, for example, the authority
fails to inform the complainant immediately of its decision
to exclude him. In such a case, the time limit ought
to start to run only from the date on which the complainant
became aware (or ought to have become aware) of the
decision to exclude him.
Procedure
<Top>
Duty
to give notice
Proceedings under the Regulations may not be brought
unless the complainant has first informed the awarding
authority of the breach or alleged breach and of his
intention to bring proceedings in respect of it. A ruling
of the High Court has indicated that this is a strict
procedural requirement and that any failure to inform
the authority both of the alleged breach and the intended
action will render the action inadmissible. It is advisable
that such notice is given in writing.
Applications for interim orders <Top>
A complainant who seeks an interim measure such as an
injunction will deal with the matter by an application
by means of a summons to the Court together with a supporting
affidavit (sworn statement). This may initially be dealt
with by the Court before the summons and affidavit are
served on the other party (ie. ex parte) but will then
be dealt with at a subsequent hearing at which the other
party may be present (inter partes). A claim for an
interim injunction will not normally involve oral evidence
but will, instead, involve lawyers making submissions
to the judge on the basis of the affidavit evidence.
The
summons for interim relief may be issued prior to, simultaneously
with, or after the issue of a writ (see Ordinary court
procedure below) but, where the summons is issued prior
to the issuing of a writ, it would be usual for the
complainant to have to give an undertaking to issue
and serve a writ. The applicant for an injunction will
usually have to give an undertaking that he will pay
damages for any loss suffered if, at the final hearing
of the proceedings, the application for the injunction
loses the case. Similar (but not identical) procedures
apply in relation to interim injunctions in the context
of judicial review proceedings (see below).
Ordinary
court procedure <Top>
Proceedings in the High Court are normally commenced
by writ. This must be endorsed with either a full statement
of the plaintiff's claim or a concise statement of the
nature of the claim and the relief or remedy being sought.
Once the court has issued the writ, it must be served
on the defendant within 4 months. A series of formal
documents (pleadings) then pass between the parties
setting out their respective cases. The pleadings should
contain only material facts and should not normally
contain statements of law. The plaintiff's first pleading
is his Statement of Claim (which may be part of the
writ). The defendant subsequently answers with a Defence,
and other pleadings may follow. Pleadings are deemed
to close 14 days after service of the last pleading
in the action, although the court may permit further
amendments.
After
the close of pleadings, the rules of the High Court
provide that discovery shall automatically take place
between the parties to the action. Discovery comprises
two stages: disclosure by way of a list of documents
by one party to the others of all relevant documents;
and inspection by the other party of such of those documents
as are not legally privileged. The scope of discovery
is very wide and extends to all documents that are or
have been in a party's possession, custody or power
relating to any matter in question in the case, save
for those which are legally privileged (eg. communications
between a party and his solicitor).
Within
one month of close of pleadings the plaintiff must take
out a summons for directions. This provides an opportunity
for the court to consider the preparations for trial
of the action. Among other things, the directions will
deal with witness statements and expert evidence.
Witness
statements are prepared in order to support a case and
are the equivalent of the factual oral evidence that
is to be given if the witness is called at trial. They
should therefore be comprehensive, as evidence of matters
not covered in the statement will only be permitted
at trial with the leave of the court. Expert evidence
may be appropriate in some procurement proceedings.
Experts will be able to give opinion evidence on any
relevant matter on which they are qualified to speak.
Witness statements and the reports of expert witnesses
must normally be disclosed to the other parties in advance
of the trial.
The
case will normally be tried by a single Judge of the
High Court without a jury and is usually in public.
At the trial the parties are normally represented by
lawyers (usually barristers) who make submissions on
their behalf and examine and cross-examine witnesses,
who give oral evidence.
Duration
of proceedings<Top>
Interim measures can be sought and obtained almost immediately
in the High Court in cases of urgency. The applicant
would be required to set out the urgent circumstances
in an affidavit to the Court. The time taken for the
matter to proceed to full trial and final judgment varies
greatly from case to case and depends to some extent
upon the workload of the division of the High Court
in which the case is lodged. As a very general estimate,
the time lag between initiation of the proceedings and
the final judgment can be anything from one to two years.
If
the case raises difficult questions of EU law, the national
court may refer questions of interpretation to the European
Court of Justice for a so-called "preliminary ruling".
Such a reference would be likely to add at least two
years to the duration of proceedings in the national
court. In practice, this kind of reference is only made
in a small minority of cases.
Finally,
it should be noted that any appeal against the High
Court ruling to the superior courts (see below) will
add many more months of delay before the case is finally
decided.
Judicial review <Top>
An alternative, and completely distinct, approach is
to proceed by way of judicial review. This is the traditional
procedure by which third parties have been able to challenge
the actions and decisions of public authorities in the
UK. The existence of the Regulations means it is no
longer obligatory to challenge public procurement decisions
by way of judicial review, but this option is still
open (as confirmed by the statement in the Regulations
that their application is without prejudice to the availability
of other remedies).
The
aggrieved person wishing to bring judicial review proceedings
must initially apply to a Judge of the High Court for
leave to do so. This is perhaps the main drawback of
using judicial review rather than bringing an ordinary
action under the Regulations. Indeed, the existence
of the latter avenue could be one reason why a judge
refuses to grant leave for judicial review. Any application
for leave must be made promptly and, in any event, within
3 months from the date when the grounds for the application
arose unless there is good reason for extending the
period. If leave is granted (which may involve consideration
of papers only or a hearing open to the public), the
substantive application proceeds and the matter is heard
by a Judge or Judges of the High Court (and is normally
open to the public).
Judicial
review proceedings are usually determined by reference
to affidavit (rather than oral) evidence without some
of the other formal procedures which apply in ordinary
civil cases. There is often little or no discovery.
The following remedies are available in judicial review
proceedings: an order restraining the decision-making
body from acting outside its jurisdiction (prohibition)
or quashing and requiring it to reconsider the matter
(certiorari); an order requiring the body to carry out
its judicial or other public duty (mandamus); the granting
of a declaration as to the rights of the parties; the
granting of an injunction; and, depending on the type
of claim, in limited circumstances, an award of damages
against the decision-making body. It can be seen that
these remedies closely overlap with those available
under the Regulations, although the right to damages
is much more limited.
There may be circumstances in which it is advantageous
for a complainant to bring an action alleging infringements
of the Regulations by way of, or in combination with,
an action for judicial review. This is a complex issue
upon which the complainant may well need to take legal
advice.
Is it necessary to engage a lawyer? <Top>
It is normal practice in High Court litigation for both
parties to instruct solicitors to act on their behalf,
both in order to deal with the complicated procedural
requirements and to present each side's arguments on
the law and merits. Furthermore, under the rules governing
High Court practice, most oral submissions can only
be presented by counsel (ie. a barrister rather than
a solicitor). Consequently, it is usually necessary
for the instructed solicitors to instruct counsel (complainants
cannot usually instruct a barrister directly themselves).
The cost implications of instructing lawyers are considered
below.
It
is possible for a complainant to represent himself in
the proceedings, but this is very rare and not generally
recommended.
Costs
of proceedings <Top>
A relatively small court fee, in the sum of £500
in this type of case, is payable upon the commencement
of proceedings. More importantly, a complainant will
need to bear in mind the cost of instructing lawyers
in order to pursue litigation. The overall cost of doing
so will depend on the gravity, complexity and duration
of the case and is difficult to predict at the outset.
It
is normal practice for the High Court to order the unsuccessful
party in the litigation to pay a large part of the legal
costs of the successful party. This is an additional
risk to be taken into account when embarking upon litigation.
Moreover, if the complainant was successful in obtaining
an injunction at an interim stage but ultimately lost
the case at the final hearing, he might find himself
liable to pay damages to the defendant under the terms
of a
cross-undertaking in damages. Complainants are often
required to give such a cross-undertaking in order to
obtain the injunction.
Rights
of appeal <Top>
Once the High Court has laid down its judgment, the
unsuccessful party may seek to appeal the ruling to
the Court of Appeal. In some cases the leave of the
judge or the Court of Appeal may be needed. This means
that permission is required before the appeal can be
brought and courts will consider a number of matters,
including the prospect of success, when deciding whether
or not to grant leave. The judgment of the Court of
Appeal may in turn be appealed, with leave, to the House
of Lords, which is the highest judicial authority in
the UK.
Enforcement of judgments<Top>
It is highly unlikely that an awarding authority would
choose deliberately to contravene a High Court order
made against it, particularly in view of the severe
penalties that may follow. If an authority disobeyed
the terms of injunction, the complainant could apply
for the committal of its officials to prison (although
the court would probably give the authority a warning
at first hearing in order to induce compliance). In
the case of judgments for damages, the complainant could
apply for an order to appropriate the authority's assets.
Useful Addresses <Top>
The High Court in London:
Royal
Courts of Justice
Strand
London WC2A 2LL
The
Court of Session in Scotland:
Parliament
House
Parliament Square
Edinburgh EH1 1RQ
The
High Court in Northern Ireland:
Royal
Courts of Justice
Chichester Street
Belfast BT1 3JF
In addition, district registries of the High Court (and
Court of Session in Scotland) are located in numerous
towns and cities throughout the United Kingdom.
The
Procurement Policy Unit (PP) within the Office of Government
Commerce (OGC) is a joint Treasury/ DTI unit responsible
to Treasury Ministers on domestic procurement policy
and the implementation of the EC rules. It is responsible
to DTI Ministers on EC procurement policy and the development
of the EC directives and other international measures
and co-ordinates all correspondence with the European
Commission on procurement matters.
Office
of Government Commerce: <Top>
Procurement
Policy Unit
Fleetbank House
2-6, Salisbury Square
London EC4Y 8AE.
Tel: 020 7211 1336
Fax: 020 7211 1344
All information in this Guidance is checked and believed
to be correct, but cannot be so guaranteed and the publishers
shall not be liable for any loss suffered directly or
indirectly as a result of its use.